British Gas Business
Supplier to London Borough of Camden
Spend by year
£0£46.5k£92.9k
2018/192020/212022/232025/26 so far
Financial years run April to March. 2025/26 is the year so far, shown dashed.
Show the figures
| Financial year | Spend | Payments |
|---|---|---|
| 2018/19 | £3,553 | 4 |
| 2019/20 | £73,991 | 33 |
| 2020/21 | £55,286 | 37 |
| 2021/22 | £92,941 | 52 |
| 2022/23 | £15,396 | 17 |
| 2023/24 | £17,933 | 16 |
| 2024/25 | £47,038 | 12 |
| 2025/26 (so far) | £13,189 | 14 |
Latest payments
| Date | Supplier | What for | Category | Amount |
|---|---|---|---|---|
By category
| Category | Total |
|---|---|
| Electricity | £152.5k |
| GAS | £100.8k |
| Capital Other Project Costs | £60.6k |
| Capital Other Works | £2,474 |
| COMPENSATION | £882 |
| Community Support | £781 |
| Capital Main Works | £677 |
| Service Charges | £612 |
Across London