Standage & Co Ltd
Paid by 8 London authorities
Total received£46.5m
Payments691
Councils8
Spend by year
£0£4.5m£8.9m
2017/182020/212022/232024/252026/27 so far
Financial years run April to March. 2026/27 is the year so far, shown dashed.
Show the figures
| Financial year | Spend | Payments |
|---|---|---|
| 2017/18 | £161,550 | 6 |
| 2019/20 | £1,421,723 | 19 |
| 2020/21 | £5,206,651 | 104 |
| 2021/22 | £7,024,547 | 87 |
| 2022/23 | £8,935,484 | 125 |
| 2023/24 | £7,225,294 | 120 |
| 2024/25 | £7,958,067 | 145 |
| 2025/26 | £8,106,050 | 76 |
| 2026/27 (so far) | £510,572 | 9 |
By council8
| Council | Total | Payments |
|---|---|---|
| Southwark | £25.7m | 450 |
| Greenwich | £14.8m | 149 |
| Wandsworth | £2.9m | 34 |
| Westminster | £1.9m | 36 |
| Hackney | £689.4k | 8 |
| Tower Hamlets | £373.6k | 8 |
| Haringey | £78.7k | 5 |
| Lewisham | £7,247 | 1 |
Companies House
- Registered name
- Standage & Co. Limited
- Company number
- 00345675
- Status
- Active
- Incorporated
- 28 Oct 1938
- Registered in
- London
- What it does
- Other construction installation
Painting
Controlled by
- Mr Christopher Brain
Matched by name to the Companies House register. Check the company number before relying on it.
By category
| Category | Total |
|---|---|
| CONSTRUCTION MAIN CONTRACT -CERTIFICATED | £17.6m |
| Refurbishment | £10.3m |
| Security Services | £4.1m |
| General Payments | £4.0m |
| CAPEXP Construction Work | £2.5m |
| CONSTRUCTION | £2.0m |
| Payments to main contractor | £763.7k |
| Y30003 CONTRACTORS - CONSTRUCTION | £689.4k |
| Term Consultancy Fees | £581.0k |
| AGENCY STAFF | £503.2k |
| CONSTRUCTION MAIN CONTRACT | £465.2k |
| Building Works - Main Works | £373.6k |
Other names2
Councils spell this supplier more than one way. These spellings are counted together on this page.
- Standage And Co Ltd