Milestone Contracting Limited
Paid by 6 London authorities
Total received£9.2m
Payments179
Councils6
Spend by year
£0£1.9m£3.8m
2021/222022/232023/242024/252025/262026/27 so far
Financial years run April to March. 2026/27 is the year so far, shown dashed.
Show the figures
| Financial year | Spend | Payments |
|---|---|---|
| 2021/22 | £1,842,628 | 9 |
| 2022/23 | £1,388,172 | 19 |
| 2023/24 | £3,760,288 | 67 |
| 2024/25 | £597,585 | 42 |
| 2025/26 | £1,437,702 | 34 |
| 2026/27 (so far) | £128,915 | 8 |
By council6
| Council | Total | Payments |
|---|---|---|
| Camden | £4.2m | 42 |
| Kensington and Chelsea | £2.5m | 49 |
| Wandsworth | £1.4m | 43 |
| Harrow | £900.5k | 15 |
| Hammersmith and Fulham | £125.5k | 29 |
| Lewisham | £571 | 1 |
By category
| Category | Total |
|---|---|
| Capital Main Works | £3.8m |
| Statutory Year-End Adjustments | £1.3m |
| Build Maint Exit Cst | £900.5k |
| Vacants | £781.0k |
| Acquisition of land & existing buildings | £703.3k |
| Capital Other Project Costs | £410.9k |
| New construction, conversion & renovation HRA | £270.4k |
| CAPEXP Construction Work | £243.6k |
| CAPEXP HRA House Purchase | £176.2k |
| General Repairs Non S/C | £156.8k |
| Reactive Repairs & Maintenance - Buildings - Repairs & Maintenance | £121.6k |
| New Construction, Conversion And Renovation Hra | £82.1k |
Other names1
Councils spell this supplier more than one way. These spellings are counted together on this page.
- Milestone Contracting Ltd