Morgan Sindall Construction & Infrastructure Ltd
Supplier to London Borough of Camden
Spend rose 6% in 2024/25, from 2023/24
Spend by financial year
Spend rose 2-fold from £8.9m to £18.2m between 2023-24 and 2025-26.
Source: Council payment files over £500
| Financial year | Spend |
|---|---|
| 2023-24 | £8.9m |
| 2024-25 | £9.4m |
| 2025-26 | £18.2m |
Financial years run April to March. 2025/26 is the year so far, shown dashed.
Show the figures
| Financial year | Spend | Payments |
|---|---|---|
| 2023/24 | £8,924,107 | 17 |
| 2024/25 | £9,415,926 | 21 |
| 2025/26 (so far) | £18,201,551 | 21 |
Latest payments
| Date | Supplier | What for | Category | Amount |
|---|---|---|---|---|
By category
| Category | Total |
|---|---|
| Capital Main Works | £35.0m |
| Capital Other Project Costs | £1.1m |
| Capital Demolition and Site Clearance | £336.7k |
| Capital Professional Fees | £95.6k |
Companies House
Morgan Sindall Construction & Infrastructure Ltd, company 04273754