Kcc Laser Interface Only
Supplier to London Borough of Bexley
Spend fell 58% in 2025/26, from 2024/25
Spend by financial year
Spend fell 56% from £544k to £238k between 2022-23 and 2026-27. Its high was £904k in 2024-25.
Source: Council payment files over £500
| Financial year | Spend |
|---|---|
| 2022-23 | £544k |
| 2023-24 | £584k |
| 2024-25 | £904k |
| 2025-26 | £379k |
| 2026-27 | £238k |
Financial years run April to March. 2026/27 is the year so far, shown dashed.
Show the figures
| Financial year | Spend | Payments |
|---|---|---|
| 2022/23 | £543,893 | 64 |
| 2023/24 | £583,562 | 93 |
| 2024/25 | £903,761 | 85 |
| 2025/26 | £379,055 | 43 |
| 2026/27 (so far) | £238,211 | 28 |
Latest payments
| Date | Supplier | What for | Category | Amount |
|---|---|---|---|---|
By category
| Category | Total |
|---|---|
| Electricity | £1.9m |
| GAS | £453.8k |
| Finance And Corporate | £297.6k |